FACT SHEET: Trump’s Cuts Threaten Pennsylvania’s Grid
Last Updated: 1/26/26
Trump’s efforts to cut federal funding from the Bipartisan Infrastructure Law and Inflation Reduction Act threaten at least $93 million in projects across Pennsylvania aimed at improving the state’s electric grid. Between 2000 and 2023, Pennsylvania had 82 weather-related power outages, the ninth most in the U.S.
As climate change continues to increase the frequency and severity of extreme weather events, without investments in modernizing and upgrading Pennsylvania’s electric grid, Pennsylvanians could be left in the dark. Trump’s push to pull the rug out from underneath transmission projects will place the Keystone State’s grid at further risk – and consumers will be left paying the price for transmission improvements and upgrades needed to meet energy demand.
- Trump’s Funding Cuts And Attacks On Federal Investments Threaten Pennsylvania’s Grid, Further Exposing Consumers To Rising Costs And Potential Blackouts
- Utilities Are Already Passing The Costs Of Grid Investments And Increased Energy Needs Onto Customers
- Pennsylvania’s Grid Is Already Vulnerable Due To Extreme Weather And The Strain Of Increased Demand
Trump’s Funding Cuts And Attacks On Federal Investments Threaten Pennsylvania’s Grid, Further Exposing Consumers To Rising Costs And Potential Blackouts
- Trump’s cuts threaten at least $93 million in clean energy projects to make Pennsylvania’s electric grid more resilient to extreme weather events.
- Pennsylvania was awarded over $24 million over five years from the U.S. Department of Energy’s Preventing Outages and Enhancing the Resilience of the Electric Grid Grants, funded through the Bipartisan Infrastructure Law, to improve resilience and enhance the reliability of its electric grids.
- Pennsylvania received over $69 million from the U.S. Department of Energy’s Smart Grid Grants, funded by the Bipartisan Infrastructure Law, to develop and improve grid resilience technologies.
- Duquesne Light Company was awarded over $19 million to invest in grid modernization projects in Allegheny and Beaver counties over the next five years.
- PPL Electric Utilities Corporation was awarded over $49 million for grid modernization projects in Central and Eastern Pennsylvania.
- Funded by the Bipartisan Infrastructure Law, PECO Energy Company (PECO) received $100 million from the U.S. Department of Energy to reduce the impacts of extreme weather and historic flooding on its electric distribution system and improve service for customers across Southeastern Pennsylvania.
- The Pennsylvania Public Utility Commission received over $4.5 million to accelerate the permitting of high-voltage, interstate transmission projects and support community infrastructure projects along major new and upgraded transmission lines. The funding came from the Transmission Siting and Economic Development (TSED) Grant Program, which was established by the Inflation Reduction Act.
- In November 2025, Prysmian Cable announced it would lay off 150 workers at its Schuylkill Haven, Pennsylvania, manufacturing facility and close the facility in 2027. Prysmian manufactured underground and submarine cables for power transmission and distribution at the facility.
Utilities Are Already Passing The Costs Of Grid Investments And Increased Energy Needs Onto Customers
- In December 2024, Governor Shapiro filed a complaint against PJM’s proposed $12.5 billion increase that its electric customers would have had to pay.
- Over the last several years, demand for energy has risen rapidly but PJM has been slow to allow new power sources onto its grid – and as a result, PJM capacity prices have skyrocketed.
- In July 2024, PJM’s 2025-2026 capacity auction resulted in costs of $14.7 billion – an over 800 percent increase to consumers.
- Ratepayer advocates in Pennsylvania urged PJM to reject a proposal from NextEra Energy and Exelon to build a $1.7-billion transmission line across central Pennsylvania because of data center demand uncertainty.
Pennsylvania’s Grid Is Already Vulnerable Due To Extreme Weather And The Strain Of Increased Demand
- As of 2020, Pennsylvania ranked 23rd in the U.S. for grid reliability. Pennsylvania ranked 32nd for duration of power outages, 31st for time to restore power, and 21st for frequency of power outages.
- The average Pennsylvania consumer experienced 1.3 outages per year. The national average was 1.4 outages.
- The average power outage duration in Pennsylvania was 334 minutes. The national average was 492 minutes.
- It took 240 minutes to restore power after an outage in Pennsylvania on average. The national average was 342 minutes.
- Between 2000 and 2023, Pennsylvania had 82 weather-related power outages, the ninth most in the U.S.
- Three electric-transmission zones that are wholly or partly in Pennsylvania are expected to see sharp increases in power demand from current and new data centers in the next few years.
- PPL, supplying a region that includes Harrisburg and Scranton, is expected to see its summer peak load demand jump more than 60 percent by 2030.
- The Allegheny Power Systems region’s load is expected to rise from 8,700 MW to a peak of nearly 10,000 MW by 2030.
- ATSI is forecast to increase its peak load demand from 12,800 MW to more than 14,400 MW by 2030.