STATE OF PLAY 

As of July 2026, Alaska had nearly 1 GW of clean energy operating or planned, enough to power an estimated over 170,000 homes. Alaska’s clean energy industry employs over 5,500 workers, a nearly 14% increase since 2020. Alaska is also home to eight planned or operating data centers, which require more power capacity than any current power plants in Alaska, and the state is already facing an impending gas shortage. 

KEY 2026 RACES
AK-SENAK-AL

ENERGY BREAKDOWN

CLEAN ENERGY PROJECTS & JOBS

Clean Energy Projects Announced Since IRA Passage
Project SummaryProjected Jobs InvestmentProject Status
Shovel Creek WindIn October 2022, Alaska Renewables proposed Shovel Creek Wind, a 200-megawatt wind farm located northwest of Fairbanks, Alaska. The company said the project would cost $800 million. As of March 2025, Alaska Renewables was collecting data for the site, which was expected to start producing electricity in 2028–$800 millionAnnounced
Little Mount Susitna WindIn October 2022, Alaska Renewables first announced Little Mount Susitna Wind, a proposed 250-megawatt wind farm northwest of Anchorage, Alaska. The wind farm was expected to generate enough power to meet 20 percent of electricity demand in Southcentral Alaska. As of March 2025, Alaska Renewables was collecting data for the proposed site.––Announced

Additional projects threatened or canceled in the state due to threats to clean energy:

Additional Threatened Or Canceled Clean Energy Projects
Project SummaryProjected Jobs InvestmentProject Status
Renewable IPP Clear Solar FarmIn February 2025, Renewable IPP announced it would no longer lead the development of a new solar farm in Clear, Alaska. Renewable IPP said the project was no longer profitable due to high costs and uncertainty over federal tax credits, which had been factored into the projected costs of developing the project.––Canceled
Renewable IPP Houston Solar FarmIn February 2025, Renewable IPP announced it would no longer lead development of an expansion of an existing solar farm in Houston, Alaska. Renewable IPP said the project was no longer profitable due to high costs and uncertainty over federal tax credits, which had been factored into the projected costs of developing the project.––Canceled
Renewable IPP Nikiski Solar FarmIn February 2025, Renewable IPP announced it would no longer build a planned solar farm in Nikiski, Alaska. Renewable IPP said the project was no longer profitable due to high costs and uncertainty over federal tax credits, which had been factored into the projected costs of developing the project. The proposed solar farm in Nikiski would have powered about 9,000 homes on Alaska’s Kenai Peninsula at a lower cost than natural gas, currently the leading generation source for the region, lowering electricity rates in the region.––Canceled

Other projects in the state, started before the Inflation Reduction Act:

Project or Company NameProject DetailsProject Status
Thermo-Kool of AlaskaThermo-Kool of Alaska is based in Wasilla and manufactures cellulose insulation. Operating
Graphite OneThe Graphite One project plans to mine, process, and manufacture anode materials primarily for artillery and missile systems and the lithium‐ion electric vehicle battery market. The project is being developed in Nome and has around 50 on-site workers. Announced
InsulfoamInsulfoam has a manufacturing facility in Anchorage. Announced
Willow Solar FarmThe Willow Solar Farm opened in 2019 in Willow. The project hired over a dozen people. Operating
Golden Valley Electric Association Solar FarmThe Golden Valley Electric Association’s solar farm opened in October 2018 in Fairbanks. Operating
Eagle and Kaltag Solar ProjectsREF has two solar projects in the communities of Kaltag and Eagle. Operating